Construction Phase
Amayo Wind Consortium had the company for the construction of Phase I, with the participation of people as workers for the work, being engineers.
Suzlon Wind Energy A / S, the Danish branch of Suzlon, India Company who is among those leading wind turbine manufacturers in the world, is supplying the turbines, towers, and auxiliary equipment.
Construction phase:
- Roads: new roads and repair existing ones according to engineering specifications.
- 19 foundations excavated and 18 completed the first phase of concrete poured
- 19 m in diameter and 2.6 meters deep.
- Steel erection
- Concrete: Almost completed the first phase. The pouring of concrete for Phase 2 began the week of May 25.
- Movement of land for construction of the electrical substation, control building and warehouse.
- Transport of wind turbine parts from Corinth to the Project.
|
|
|