Construction Phase

Amayo Wind Consortium had the company for the construction of Phase I, with the participation of people as workers for the work, being engineers.

Suzlon Wind Energy A / S, the Danish branch of Suzlon, India Company who is among those leading wind turbine manufacturers in the world, is supplying the turbines, towers, and auxiliary equipment.

Construction phase:

  1. Roads: new roads and repair existing ones according to engineering specifications.
  2. 19 foundations excavated and 18 completed the first phase of concrete poured
  3. 19 m in diameter and 2.6 meters deep.
  4. Steel erection
  5. Concrete: Almost completed the first phase. The pouring of concrete for Phase 2 began the week of May 25.
  6. Movement of land for construction of the electrical substation, control building and warehouse.
  7. Transport of wind turbine parts from Corinth to the Project.